Calala Battery Energy Storage System
Equis is developing a 300MW/600MWh Battery in Calala, Tamworth to help provide New South Wales with reliable energy.
Community drop-in session
Project Schedule
Community drop-in session
Project Schedule
Equis completed its first community drop-in session on the 14th of December 2022 at the Best Western Plus All Settlers Motor Inn between 3pm and 7pm.
The proposed Calala Battery Energy Storage System (BESS) is located approximately 5.8km southeast of the Tamworth CBD within the Tamworth regional municipality. The BESS has a charge/discharge capacity of up to 300MW and an energy storage capacity up to 600MWh which is enough power to supply electricity for up to 570,000 homes for two hours.
The BESS site will be connected to NSW’s electricity grid via an underground cable that connects to the 330kV . Tamworth Substation. The project will help meet NSW’s future electricity demands. The BESS will provide significant local benefits during construction and operation including investment in the local economy. The BESS will create approximately 170 full times jobs during construction and 7 during operations as well as funding community programs.
The Calala Battery Energy Storage System will allow for increased solar and wind energy to be integrated into the grid helping to reduce volatility and lower electricity prices.
THE LOCAL
COMMUNITY
AND
AND
ENVIRONMENT
Planning and Environment Approvals
Equis submitted an Environmental Impact Statement to the NSW Department in November 2023 for assessment.
Further information on the Project and the development assessment can be viewed on the NSW's Major Projects webpage and our Engagement Hub webpage below.
Community benefits
Direct programs to support the local community
170
Construction Jobs
07
Operational Jobs