MREH is being supported by Tier 1 contractors across the construction process.

MREH is being supported by Tier 1 contractors across the construction process. Tesla will supply the Megapack 2XL battery technology and oversee the commissioning of MREH Side A.

Samsung C&T Corporation and GenusPlus Group joint venture will conduct the BOP works for MREH. Lumea is delivering the contestable connection assets for MREH as part of its delivery of the MREH substation, the Plumpton Renewable Terminal Station.

Finally, AusNet will manage non-contestable augmentation at the Sydenham Terminal Station. Each contractor’s expertise is crucial for MREH’s overall success.